BRINGING YOUR NEW COMMUNITY TO LIFE

As we progress with building your new community, there are several important elements that help transform a construction site into a fully completed neighbourhood. These are known as Estate Completion Works and include the finishing of roads, open spaces, essential infrastructure, and any required works outside the development.
The sections below outline the key areas of work, what they include, and our current estimated completion timelines.

OPEN SPACES

This will include our commitment to install surface water ponds, open spaces public open space and recreational areas.
Open space areas Ongoing
Recreational areas like formal play areas, street signage and road name signs; completion date Various Areas Ongoing
Surface water ponds Ongoing
Other

ESTATE INFRASTRUCTURE

This may include items like electric substations, pumping stations, communal areas etc.
Pumping station By end of development
Electric substation Air Source Heat Pumps
Community buildings, schools, allotments N/A

ROADS

During the phases of construction, we work with our subcontractors to roads construct the roads to a ‘base off site works course’. This is suitable for all traffic to drive on and is the penultimate stage prior to the finished surface being laid. The roads are then completed on a phased basis as complete various sections of the development. These future phases estate infrastructure phases are determined to avoid surfaces becoming damaged by construction traffic. The completion and adoption of these areas are also dictated by third party influences such as the Local Authority. The roads will remain the property of Wain Homes until they are taken over by the Local Authority or management company. All maintenance will be the responsibility of Wain Homes until the hand over occurs.
Road and footpath construction to ‘base course’ Ongoing
Final surfacing First phase of development completion
Street lighting As site develops